March 8, 2013
Well, the sun came out and we had a big day. Got up at 430 and continued forming at first light (600) to be ready for the concrete gang arriving by barge at 9am. Three trucks, 9 guys and 6 hours later all was completed. The form system held up well and things should be ready for stripping tomorrow. We are going to slow down a bit and catch our breath now that the foundation is complete. Dana worked all day with the excavator operator (Kevin) planting trees – looking good but still another day to go. Happy bday Sarah!!